There will be restricted access to some walkways on the Auraria Campus starting Thursday, due to the installation of a steam line along the south side of the North Classroom Building and across 11th Street to support the Auraria Science Building expansion.
The installation will take place in two phases. The first, beginning June 18, will restrict pedestrian access to the North Classroom. The second phase, beginning June 25, will restrict access to the Auraria Campus via 11th Street and the North Classroom.
The steam line work and closures are anticipated to be complete by July 15.
For questions, contact Brady Babbitt at 303-556-4624 or Mike Turman at 303-556-2394.